After a prolonged closure, the Haldia Petrochemicals Ltd (HPL) plant is in the process of re-starting operations with the trial run to begin in the near future, as per thehindubusinessline.com. “The captive power plant has been commissioned as a pre-start up activity. The main plant start-up should happen anytime now,” a source in HPL told PTI, adding that stabilisation of the power plant would take some days, after which steps would be initiated for operating the mother plant, closed since July 2014.
Earlier, the West Bengal Government had provided Rs. 100 crore as margin money as demanded by the lenders, while the other promoter, TCG, was yet to furnish that amount. TCG has agreed to come up with the margin money, while the lenders have also committed funds for running the plant.