Covestro increases MDI production capacity - to convert existing, idled plant for TDI

01-Jul-16

Covestro is moving forward with a repurposing of its production operations in Brunsbüttel, Germany. The Board of Management has now officially approved an expansion of production capacity for the foam component MDI at the site. An existing, idled plant for the precursor TDI will be converted for production of MDI. The plans call for roughly doubling production capacity at the site to a total of approximately 400,000 metric tpa of MDI. Commissioning of the new plant complex is scheduled for late 2018. Preliminary plans call for a total investment volume (in euros) in the low hundreds of millions, which is already included in Covestro’s medium-term capital expenditure budget. The Covestro Brunsbüttel Industrial Park is particularly well-suited for the MDI expansion because raw materials and other precursors are available there, and the site also offers the infrastructure required. Furthermore, the site’s employees also have extensive expertise and experience.

MDI (diphenylmethane diisocyanate) is the basis to produce rigid polyurethane foam, which is used primarily for the efficient insulation of buildings and throughout the cool chain. The resultant energy savings help to substantially reduce COemissions. TDI (toluene diisocyanate), on the other hand, is a key component of flexible polyurethane foam, which is found in products including mattresses, upholstered furniture and automobile seats. The Dormagen site is Covestro’s European center for production of this precursor.
The planned MDI plant complex is a milestone in terms of energy efficiency, environmental compatibility and productivity, in addition to meeting the highest safety standards,” said Dr. Steffen Kühling, site and production manager in Brunsbüttel. He added that the project also represents a clear commitment to the Brunsbüttel site and will help to secure jobs at the plant and in the region. 
The public authorities granted Covestro the permit for converting the plant in March 2014. This allows annual capacity to be expanded by as much as 220,000 metric tons of MDI. During the conversion, some 300 employees of participating service providers will be working at the site.
 

  More News  Post Your Comment

Previous News

Next News

{{comment.Name}} made a post.
{{comment.DateTimeStampDisplay}}

{{comment.Comments}}

COMMENTS

0

There are no comments to display. Be the first one to comment!

*

Email Id Required.

Email Id Not Valid.

*

Mobile Required.

*

Name Required.

*

Please enter Company Name.

*

Please Select Country.

Email ID and Mobile Number are kept private and will not be shown publicly.
*

Message Required.

Click to Change image  Refresh Captcha
Moulds for lotion pump

Moulds for lotion pump